Construction Coordination

Pioneer Square faces unique challenges as an unprecedented number of transit and development projects come on line. The Alliance coordinates with many of the following projects, working to limit negative impacts from construction, and advocate for positive neighborhood enhancements where appropriate. Stay up to date and find information on existing projects below:

Construction Coord

Building Projects

200 Occidental – 8-story office building located at 200 Occidental Ave S
Expected completion – completed Fall 2016

450 Alaskan Way – 8-story office building located at 450 Alaskan Way S
Expected completion – Fall 2017

Gridiron – 10-story, 107 residential unity building located at 589 Occidental Ave S
Expected completion – Summer 2017

North Lot/Stadium Place – High-rise residential, office, and hotel towers north of Century Link Stadium
Expected completion – mid 2017

Transportation and Utility Projects

Alaskan Way Viaduct Replacement Project – Includes the tunneling of SR-99 and the replacement of the Alaskan Way Viaduct
Expected completion – TBD

Nord Alley and Pioneer Passage – Infrastructure upgrades and new alley surfaces
Surface Construction winter/spring 2017

Yesler Bridge – Rehabilitation of the historic Yesler Bridge
Expected completion – Fall 2017

Seawall Project – Replacement of existing infrastructure
Expected completion – Summer 2017

Colman Dock Project – Replacement of the existing Washington State Ferry Terminal
2015-2017 – Final design and permitting
2017-2023 – Construction

Central City Connector – Streetcar project for 1st Ave, connecting the two existing streetcar lines
Utility Work starts Q3 2017