This Week: October 15th – October 21st
Full PDF copies of these updates are attached:
Weekly Project Update – Jackson #20
Weekly Project Update – Broadway #26
Weekly Project Update – Yesler #23
BROADWAY SEGMENT – CONSTRUCTION DETAIL
Weekend Intersection Closure at Broadway and Madison,
Weekend Closure at James
Weekday Work:
7:00 a.m. – 4:00 p.m.
- Howell and Nagle
- o Electrical duct bank installation
- Pike to Madison
- o Trackway construction
• Columbia intersection
- o Steam vault modifications
- James and Jefferson intersections
- o Electrical installation
- Cherry intersection
- o Storm drain installation
- Cherry to Jefferson
- o Trackway construction
Weekend Work:
- Madison intersection
- o Water main work
- James intersection
- o Track construction
Traffic Advisory:
- The east leg of the Broadway/Madison intersection will be closed this weekend (7:00 a.m. – 7:00 p.m.)
- This weekend, October 19th – 22nd, James Street will be closed to through traffic at Broadway (Friday, 6:00 p.m. – Monday, 5:00 a.m.)
14TH/YESLER SEGMENT – CONSTRUCTION DETAIL
Water Main & Storm Drain Installations
Weekday Work:
- Broadway at Boren
- o Storm drain installation
- Broadway at Fir
- o Water main installation
- Yesler – Broadway to Boren
- o Water main installation
- Jackson – 12th to 14th
- o Street restoration
Work Hours:
- Weekdays – 7:00 a.m. – 7:00 p.m.
JACKSON SEGMENT – CONSTRUCTION DETAIL
Water Main & Electrical Duct Bank Installations
Weekday Work:
- Electrical duct bank installation between 1st and 2nd
- Water main installation and service transfers between 6th and 7th
Work Hours:
- Weekdays 7:00 a.m. – 4:00 p.m.
Note on Water Main Shutoffs:
The first of three area-wide water shutoffs in the Chinatown/International District was completed the weekend of October 6-7. The remaining shutoffs will begin at 10:00 p.m. on Saturdays and continue until 10:00 a.m. on Sundays and are tentatively scheduled for the weekends of October 27-28 and November 3-4. If your building will be affected you will receive a notice directly from Seattle Public Utilities at least 72 hours in advance.