First Hill Streetcar – Weekly Project Updates
This Week: August 20th – August 26th
This post contains project updates for all three segments: Broadway, 14th/Yesler, and the Jackson segment.
Full copies of these updates are attached in the links below.
- Broadway Segment Issue 18 – August 20,2012
- Jackson Project Update Issue 18 – August 20, 2012
- 14th & Yesler Project Update Issue 18 – August 20, 2012
BROADWAY SEGMENT – CONSTRUCTION DETAIL
Trackway Construction Between Pine and Pike
Weekday Work:
- Howell to Pine
- o Traffic signal foundations and electrical work
- Pine to Pike
- o Excavation and construction of trackway
• Marion to Columbia
- o Storm drain installation
• James to Jefferson
- o Connect water services
- Minor intersection
- o Electrical duct bank installation
Weeknight Work:
- Rail delivery to Pike
Weekend Work:
- Cherry intersection
- o Water main installation
Work Hours:
- Weekdays -7:00 a.m. – 4:00 p.m.
- Weekend Work at Cherry – Continuous work from 7:00 a.m. Saturday until 5:00 p.m. Sunday
Note Regarding Water Main Installation:
This weekend there will be a nighttime shutdown to water service from Cherry to Jefferson. If your building will be affected you will receive notice of a water shutdown directly from Seattle Public Utilities at least 72 hours in advance.
14TH/YESLER SEGMENT – CONSTRUCTION DETAIL
Expect Additional Traffic Delays This Week on Yesler
Weekday Work:
- Broadway- Boren to Yesler
- o Storm drain and sewer installation
- Yesler – Broadway to 10th
- o Storm drain and sewer installation
- Yesler – 12thto 14th
- o Trackway construction
- o Sewer main installation
- 14th– Yesler to Washington
- o Roadway and sidewalk reconstruction
- o Traffic signal foundation construction
- Main – 14th to Boren
- o Construct foundation for electrical substation
Weekend Work:
- Yesler – 12th to 14th
- o Trackway construction
Work Hours:
- Weekdays – 7:00 a.m. – 7:00 p.m.
- Saturday – 7:00 a.m. – 7:00 p.m.
JACKSON SEGMENT – CONSTRUCTION DETAIL
Water Main, Storm Drain, and Electrical Duct Bank Installation
Weekday Work:
- Electrical duct bank installation between 1st and 2nd
- Storm drain installation between 6th and 7th
- Installation of water main between 7th and 8th
Weekend Work:
- Storm drain installation at 7th
Work Hours:
- Weekdays – 7:00 a.m. – 4:00 p.m.
- Weekend –7:00 a.m. – 6:00 p.m.
Note Regarding Water Main Installation:
Beginning in late September there will be water service interruptions as new connections are made along Jackson. If your building will be affected you will receive notice of a water shutdown directly from Seattle Public Utilities at least 72 hours in advance.
More information at http://www.seattlestreetcar.org/firsthill.htm