This Week: October 8th – October 14th
Full copies of these updates are attached:
Weekly Project Update – Jackson #19
Weekly Project Update – Yesler #22
Weekly Project Update – Broadway #25
BROADWAY SEGMENT – CONSTRUCTION DETAIL
Night and Weekend Intersection Closures at Broadway and Madison,
Weekend Closure at Pike
Weekday Work:
7:00 a.m. – 4:00 p.m.
- Denny to Howell
- o Street restoration
- Howell and Nagle
- o Electrical duct bank installation
- Pine to Pike
- o Street restoration
- Pike to Madison
- o Trackway construction
• Columbia intersection
- o Steam vault modifications
- Cherry and James intersections
- o Traffic signal controls installation
- Cherry to Jefferson
- o Saw cutting
Weeknight Work:
7:00 p.m. – 6:00 a.m.
- Pike intersection
- o Track construction
- Madison to Marion
- o Storm drain installation
Weekend Work:
- Madison intersection
- o Water main work
Traffic Advisory:
- The intersection of Broadway/ Madison will be closed on weekends until November 4th
(7:00 a.m. – 7:00 p.m.)
- Broadway will be closed weeknights between Madison and Marion until October 15th with a signed detour (8:00 p.m. – 6:00 a.m.)
- On the weekend of October 12th – 15th Pike Street will be closed to through traffic at Broadway (Friday 7:00 p.m. –Monday 5:00 a.m.)
14TH/YESLER SEGMENT – CONSTRUCTION DETAIL
Water Main & Sewer Installations, Street Restoration
Weekday Work:
- Yesler – Broadway to Boren
- o Water main installation
- Yesler at 12th
- o Sewer installation
- Yesler at 14th
- o Street restoration
- Jackson – 8th to 10th
- o Water main installation
Work Hours:
- Weekdays – 7:00 a.m. – 7:00 p.m.
JACKSON SEGMENT – CONSTRUCTION DETAIL
Water Main & Electrical Duct Bank Installations
Weekday Work:
- Electrical duct bank installation between 1st and 2nd
- Water main installation between
6th and 7th
Work Hours:
- Weekdays 7:00 a.m. – 4:00 p.m.
Note on Water Main Shutoffs:
Last weekend the first of three October water shutoffs in the Chinatown/
International District was completed. The remaining shutoffs will begin at 10:00 p.m. on Saturdays and continue until 10:00 a.m. on Sundays. If your building will be affected you will receive a notice directly from Seattle Public Utilities at least 72 hours in advance.
More information at http://www.seattlestreetcar.org/firsthill.htm