First Hill Streetcar – Weekly Project Updates

This Week: October 8th – October 14th         

Full copies of these updates are attached:

Weekly Project Update – Jackson #19

Weekly Project Update – Yesler #22

Weekly Project Update – Broadway #25

 

 BROADWAY SEGMENT – CONSTRUCTION DETAIL

Night and Weekend Intersection Closures at Broadway and Madison,

Weekend Closure at Pike

Weekday Work: 

7:00 a.m. – 4:00 p.m.

  • Denny to Howell
    • o Street restoration
  • Howell and Nagle
    • o Electrical duct bank installation
  • Pine to Pike
    • o Street restoration
  • Pike to Madison
    • o Trackway construction

• Columbia intersection

  • o Steam vault modifications
  • Cherry and James intersections
    • o Traffic signal controls installation
  • Cherry to Jefferson
    • o Saw cutting

Weeknight Work:

7:00 p.m. – 6:00 a.m.

  • Pike intersection
    • o Track construction
  • Madison to Marion
    • o Storm drain installation

Weekend Work:

  • Madison intersection
    • o Water main work

Traffic Advisory:

  • The intersection of Broadway/ Madison will be closed on weekends until November 4th

(7:00 a.m. – 7:00 p.m.)

  • Broadway will be closed weeknights between Madison and Marion until October 15th with a signed detour (8:00 p.m. – 6:00 a.m.)
  • On the weekend of October 12th – 15th Pike Street will be closed to through traffic at Broadway (Friday 7:00 p.m. –Monday 5:00 a.m.)

 

14TH/YESLER SEGMENT – CONSTRUCTION DETAIL

Water Main & Sewer Installations, Street Restoration

Weekday Work:

  • Yesler – Broadway to Boren
    • o Water main installation
  • Yesler at 12th
    • o Sewer installation
  • Yesler at 14th
    • o Street restoration
  • Jackson – 8th to 10th
    • o Water main installation

Work Hours:

  • Weekdays – 7:00 a.m. – 7:00 p.m.

 

JACKSON SEGMENT – CONSTRUCTION DETAIL

Water Main & Electrical Duct Bank Installations

Weekday Work:

  • Electrical duct bank installation between 1st and 2nd   
  • Water main installation between

6th and 7th

Work Hours:

  • Weekdays 7:00 a.m. – 4:00 p.m.

Note on Water Main Shutoffs:

Last weekend the first of three October water shutoffs in the Chinatown/

International District was completed. The remaining shutoffs will begin at 10:00 p.m. on Saturdays and continue until 10:00 a.m. on Sundays. If your building will be affected you will receive a notice directly from Seattle Public Utilities at least 72 hours in advance.

 

More information at http://www.seattlestreetcar.org/firsthill.htm