Downtown Streetcar Open House Tomorrow (11/19/14)

Streetcar at Jackson & Occidental

SDOT is holding an open house on the Center City Streetcar project tomorrow evening – covering the City Council approved segment that would tie the South Lake Union and the First Hill streetcar lines together.

The open house will be from 5:00 – 7:30 PM, Wednesday, November 19, 2014 at 85 Pike Street, on the 3rd floor of the Economy Building.

This streetcar line will operate in its own lane on First Avenue (to ensure fast, reliable service) with trains arriving every 5 minutes. Stops are planned near Pike Place Market, the Marion Street Bridge to the ferries at Colman Dock and Pioneer Square.

Project staff will present information on urban design opportunities, connection options between First Avenue and Westlake, parking strategies and construction phasing throughout the event. Please drop in anytime between 5:00 and 7:30PM to find out about this exciting connection in Seattle’s future.

Alaskan Way Viaduct Replacement Program News – August 2014

BerthaTopics:

Bertha update – Construction of the access pit’s underground walls will continue through August

Earlier this week, Seattle Tunnel Partners notified us that building the underground walls of the circular pit (pdf 2.5 Mb) crews will use to access and repair the SR 99 tunneling machine will continue through August. While this date is later than anticipated, STP reports that tunneling is still expected to resume as scheduled in March 2015.

Building a self-supporting, concrete ring that is 120 feet deep and 80 feet wide is no easy task, especially given the difficult ground conditions near South Jackson Street. STP crews have completed more than half of the underground piles and are working around-the-clock, seven days a week to complete the approximately 31 remaining piles.

There are several reasons the work is taking longer than anticipated. One factor is the addition of 11 piles to the pit’s design, bringing the total number of piles to approximately 84. Crews are also working with exceptionally large interlocking piles, which are necessary to make the pit self-supporting without tiebacks or other reinforcements. A self-supporting pit is what will allow the tunneling machine to mine through its walls, but the large piles take longer to install than standard piles.

While pile work continues, crews are making progress on other areas of the repair plan on schedule, including:

  • Shipping repair pieces: The new main bearing has arrived in Seattle and will be assembled closer to the time it’s needed, likely this fall.
  • Manufacturing repair pieces: Other repair pieces, such as the new outer seal ring, the thrust seal ring and bearing block are nearing completion. After these pieces are fabricated and inspected, Hitachi Zosen will ship them to Seattle.
  • Assembling a 300-ton crawler crane: This crane will be used to help assemble the 600-ton crawler crane. Pieces of that crane will arrive in September and assembly will begin shortly thereafter.
  • Assembling a 600-ton crawler crane: This crane will be used to assemble the modular lift tower (massive red crane) that will lift the largest pieces of the machine from the access pit. Parts of that crane will also arrive in September and assembly will begin in late September.
  • Assembling the 2,000-ton modular lift tower: Starting in late July and continuing through fall, crews will begin to stage the modular lift tower. Parts of the modular lift tower will arrive over the next several months beginning in late July.

We will continue to update you on STP’s efforts to resume tunneling by March 2015. You can watch the access pit take shape on our time-lapse camera, and view photos of recent construction on Flickr.
[divider_top]

Early warning – Four-day closure of SR 99 coming in late August

In late August, crews building the future north portal of the SR 99 tunnel will close SR 99/Aurora Avenue North near South Lake Union for four days. During this closure, crews will demolish and replace the section of SR 99 that crosses above Broad Street.

To minimize the need for additional closures, separate crews will complete the following work elsewhere along the SR 99 corridor during this time:

  • Utility work at Harrison Street.
  • Concrete panel replacement in SODO.
  • Expansion joint repairs on the Alaskan Way Viaduct near the Seneca Street off-ramp.
  • Ivy removal from the viaduct.

Closure information

Drivers should plan ahead for SR 99 closures from Friday night, Aug. 22 to Wednesday morning, Aug. 27. View a map of the closure.

  • From 10 p.m. Friday, Aug. 22 to 5 a.m. Monday, Aug. 25, SR 99 will be closed in both directions from the West Seattle Bridge to Valley Street.
    • Northbound SR 99 will be open from South Royal Brougham Way until midnight on Friday, Aug. 22 for exiting Seahawks traffic.
  • From 5 a.m. Monday, Aug. 25 to 5 a.m. Wednesday, Aug. 27, SR 99 will be closed in both directions from the south end of the Battery Street Tunnel to Valley Street.

Driver tips

Travelers who use SR 99 should consider the following:

  • Allow plenty of extra time and expect additional congestion on alternate routes including I-5 and surface streets.
  • Leave early or delay your trip to avoid traveling during peak commute periods in the morning and afternoon.
  • Delay or reschedule discretionary trips.
  • Consider telecommuting.
  • Choose an alternative travel mode such as King County Metro, share a ride in a car or vanpool, or walk or ride a bicycle. 

Know before you go and have a backup plan

Those who must drive are encouraged to stay engaged and check traffic conditions frequently via WSDOT’s web, mobile and phone-based traveler information systems.

  • The Seattle traffic page contains updated road information including links to traffic cameras.
  • The travel alerts website provides real-time information about blocking incidents.
  • WSDOT’s mobile app offers information for travelers on the go.
  • @wsdot_traffic provides Twitter updates about travel issues.
  • 5-1-1 offers traffic updates.
  • The What’s Happening Now page chronicles closures and issues affecting travelers.
  • Learn more about your commute and travel choices.

[divider_top]

Milepost 31 Speakers Series – Bertha and progress on the SR 99 Tunnel Project

Seattle Tunnel Partners, the contractor hired by WSDOT to design and build the SR 99 tunnel, is working to repair the SR 99 tunneling machine. Join us to learn more about STP’s plan to resume tunneling by the end of March 2015, and learn about the other work happening to replace the viaduct.

  • 6 – 6:30 p.m.
  • Thursday, Aug. 7
  • Milepost 31, 211 First Ave. S., Seattle
  • Admission is free

[divider_top]

Seattle City Light Increasing Electrical Capacity Along 1st Avenue

cablepulling

Updated Information: Seattle City Light plans to pull in new underground power lines along 1st Avenue from King Street to Washington Street on Wednesday, February 26 and then from Washington Street to Cherry Street on Wednesday, March 5. We want you to know about the work and its impacts.

What:                  Several-day job, pulling and splicing cable

Why:                    Upgrading our system to increase electrical capacity and reliability

Where:               Vaults located in parking lane on west side of First Avenue from King Street to Washington Street and from Washington Street to Cherry Street. See maps on reverse side.

When:                 Pulling cable between King Street to Washington Street is planned for Wednesday, February 26 from 6:30 p.m. to 10:30 p.m.

Pulling cable between Washington Street to Cherry Street is planned for Wednesday, March 5 from 6:30 p.m. to 10:30 p.m.

 

Project Impacts – What you can expect:

  • No planned outages or trenching
  • City Light trucks on the street, crews working from vault to vault
  • Splicing cable has limited impacts to traffic and parking and will take place on side streets following the two nights of cable pulling.
  • Localized traffic, parking, and noise  impacts at the vaults where the work is occurring
  • Uniform police officers will direct traffic

 

No parking signs will be used for the spaces near the vaults where work is to occur. The signs will give the hours of our work and will be picked up as the work progresses if crews no longer need access to an area.  For more information about available parking in the area, please go to:  http://downtownseattle.com/parking/index.html

 

Thank you for your patience.  For any questions you may have or for more information, contact Becky Ginn, Electrical Service Representative, at 206-386-1553 or rebecca.ginn@seattle.gov.