First Hill Streetcar – Weekly Project Updates This Week: September 17th – September 23rd

BROADWAY SEGMENT – CONSTRUCTION DETAIL

Weekend Detour of Pike at Broadway

Weekday Work:

  • · Howell  – Broadway to Nagel
    • o Electrical duct bank installation
  • · Pine to Madison
    • o Trackway construction
    • o Traffic signal work

• Madison to Columbia

  • o Storm drain installation
  • · Jefferson intersection
    • o Electrical duct bank installation

Weekend Work:

  • · Pike intersection
    • o Trackway construction

Traffic Advisory:

  • · Pike will be closed at Broadway on the weekend of September 22nd and 23rd with right turns permitted at Broadway.
  • · Broadway will be closed between Madison and Marion from 8:00 p.m. to 6:00 a.m. for up to two weeks beginning September 24th. There will be a signed detour.

Work Hours:

  • Weekdays  7:00 a.m. – 4:00 p.m.
  • Saturday  7:00 a.m. – 7:00 p.m.
  • Sunday 8:00 a.m. – 5:00 p.m. 

14TH/YESLER SEGMENT – CONSTRUCTION DETAIL

Expect Traffic Delays This Week on Yesler at 10th

Weekday Work:

  • Broadway at Alder
    • o Electrical duct bank and storm drain installations
  • Yesler at 10th
    • o Sewer installation
  • Yesler – 12thto 14th
    • o Traffic signal work
  • Jackson – 8th to 10th
    • o Water main installation

Work Hours:

Weekdays – 7:00 a.m. – 7:00 p.m.

 

JACKSON SEGMENT – CONSTRUCTION DETAIL

Water Main, Storm Drain, and Electrical Duct Bank Installation

Weekday Work:

  • Electrical duct bank installation between 1st and 2nd   
  • Storm drain installation between 6th and Maynard
  • Water main installation between 8th and 10th

Weekend Work:

  • Electrical duct bank installation between 1st and 2nd
  • Water main installation between 6th and Maynard
  • Storm drain installation at 8th Avenue intersection

Work Hours:

  • Weekdays 7:00 a.m. – 4:00 p.m.
  • Weekend 7:00 a.m. – 6:00 p.m.

Note Regarding Water Main Installation:

Beginning in early October there will be water service interruptions as new connections are made along Jackson. If your building will be affected you will receive notice of a water shutdown directly from Seattle Public Utilities at least 72 hours in advance.

 

More information at http://www.seattlestreetcar.org/firsthill.htm

1st Avenue Construction Parking Impacts Update

Seattle City Light is preparing to replace old clay conduit and underground power lines along 1st Avenue between Columbia and Cherry Streets and could start work as soon as Sept. 17.

WHAT:           Trenching alongFirst Avenue to lay new conduit

WHEN:          As early as Sept. 17, lasting up to nine weeks.

TIME:             Most days work will be between 8 a.m. and 3 p.m. There will be some after-hours work.

The Seattle Department of Transportation has approved Seattle City Light’s revised traffic control plan for this project.A streetuse permit for the construction is still pending with SDOT. We will provide an update when permitting is complete and a start date is finalized.

Under City Light’s proposal, crews would work most days between 8 a.m. and 3 p.m. with some extended- or after-hours work expected. Work could last until the mid-November holiday construction moratorium begins.

A map of the construction zone is attached, detailing the traffic and parking restrictions.

The construction zone will take up the western parking lane along 1st Avenue. This is where workers will be trenching and replacing old clay conduits, which are called ducts. Crews will start the trenching work at Cherry and work north toColumbia in three sections.

One lane of southbound 1st Avenue will remain open throughout the project. Northbound traffic will have fewer disruptions. The primary travel lane will not be affected.

The parking lane on the east side of the street — which serves as a travel lane during morning and evening peak use — will have some restrictions during the final weeks of the work. Three to four parking spots near Columbia Streetwill be restricted when crews reach that end of the work zone. All parking spots south of that area along the east side of 1st Avenue will remain open when they are not affected by regular peak traffic restrictions.

Additionally, reduced-price parking is available at the 1st and Columbia Garage for $3 an hour. Whenever you’re wondering where to park on Seattle’s Waterfront of in Pioneer Square, visit www.DowntownSeattleParking.com to locate a $3 per hour space near your destination.

“No Parking” signs will be set up, prohibiting parking from 6 a.m. until 6 p.m. Monday through Friday to ensure that all vehicles are removed from the area in time for the next day of work. Existing peak hour parking restrictions already prohibit parking along 1st Avenue from 6 a.m. to 9 a.m. and from 3 p.m. to 6 p.m. Construction-related no parking signs are being labeled to match the existing peak hour restrictions. When work is done for the day, crews will cover the excavated trench with metal plates and traffic flow will be returned to normal.

Sometime in 2013, other crews will install new cable over several days. This work will be much less intrusive, involving up to two trucks and lineworkers pulling cable into place and working inside the underground vaults. The trucks will take up some parking space and the work will impact traffic flow, but is not expected to require extensive lane closures. We will update you when that work is scheduled.

This project does not involve any scheduled power outages. We do not anticipate any sidewalk impacts. There will be some noise as crews open up the street with machinery and remove the ducts.

Additionally, after City Light finishes its work, Comcast plans to install two small access vaults for their cable lines in the area, which could affect sidewalk access. We are coordinating with them to minimize interruptions to the neighborhood. Their work could last an additional two to three weeks. Look for additional details from Comcast regarding their project.

 

Thank you for your patience during this construction. For more information, contact John Harvey, Electrical Service Representative at (206) 386-4275 or (206) 459-6113 or Bob Hansen, Project Manager, at (206) 684-3387.  You can also visit our website at: http://www.seattle.gov/light/aboutus/construction/

Alaskan Way Viaduct Replacement Construction Closures – Highlights for Friday, Sept. 14 – Monday, Sept. 24

Visit WSDOT’s website for a complete list of closures. Closure information changes frequently, so remember to check for updates throughout the week.

Corridor-wide:

  • Viaduct reinforcement work will close all lanes of southbound SR 99 between the north end of the Battery Street Tunnel and the West Seattle Bridge at the following times:
    • 9 p.m. to 5 a.m. nightly. Sunday, Sept. 16 – the morning of Friday, Sept. 21.
    • 9 p.m. to 5 a.m. nightly. Sunday, Sept. 24 – the morning of Friday, Sept. 28.

 

North:

Monday, Sept. 17 through Wednesday, Sept. 19

  • Parking will close and flaggers will alternate one-way traffic on Thomas Street between Sixth Avenue North and Taylor Avenue North from 7 a.m. to 5 p.m. daily.

Monday, Sept. 17 through Thursday, Sept. 20

  • Parking will be closed around-the-clock on Harrison Street between Broad Street and Sixth Avenue North and flaggers will direct traffic from 7 a.m. to 5 p.m. daily.

Monday, Sept. 17, through Friday, Sept. 21

  • John Street will close from 7 a.m. to 5 p.m. daily between Sixth Avenue North and Taylor Avenue North, and from Aurora Avenue North to the alley.
  • Parking will close and flaggers will alternate traffic on Sixth Avenue North between Thomas and John streets from 7 a.m. to 5 p.m. daily.

 

Central:

Monday, Sept. 17

  • The north parking lane and north lane on Marion Street will close between Alaskan Way and First Avenue from 7 p.m. to 5 a.m.

Monday, Sept. 17, through Friday, Sept. 21

  • The southbound parking lane on Western Avenue between Marion and Columbia streets will be closed from 9 a.m. to 3 p.m. daily.

Tuesday, Sept. 18, through Friday, Sept. 21

  • The right travel lane and the parking lane on Marion Street between Alaskan Way and First Avenue will be closed from 7 p.m. to 5 a.m. nightly.

 

South:

Friday, Sept. 14, through Monday, Sept. 17

  • All lanes of northbound SR 99 will be closed between South Royal Brougham Way and the West Seattle Bridge from 10 p.m. Friday until 5 a.m. Monday. The on-ramps to and from South Royal Brougham Way will remain open to serve event traffic.
  • The left lane of southbound SR 99 will be closed between South Royal Brougham Way and the West Seattle Bridge from 11 p.m. Friday through 11 a.m. Saturday morning.
  • The following streets will be closed from 7 p.m. Saturday to 5 a.m. Sunday morning:
    • South Atlantic Street west of Colorado Avenue South.
    • East Marginal Way South between South Hanford Street and South Atlantic Street.

Quick links:

 

Website links

Alaskan Way Viaduct Replacement Program

SR 99 Tunnel Project | South Holgate Street to South King Street Project