Full PDF copies of these updates are attached:
Weekly Project Update – Jackson #16.5
Weekly Project Update – Yesler #20
Weekly Project Update – Broadway #23
BROADWAY SEGMENT – CONSTRUCTION DETAIL
Weekend Intersection Closure at Broadway and Union
Weekday Work:
- Denny to Howell
- o Street restoration
- Pine to Madison
- o Trackway construction
• Madison to Columbia
- o Storm drain and electrical duct bank installation
- Jefferson intersection
- o Electrical duct bank installation
Weeknight Work:
- Madison intersection
- o Storm drain installation
Weekend Work:
- Union intersection
- o Trackway construction
Traffic Advisory:
- The intersection of Broadway and Union will be closed, with the exception of one northbound lane, the weekend of September 29th and 30th.
- Broadway will be closed between Madison and Marion from 8:00 p.m. to 6:00 a.m. for up to two weeks beginning September 27th. There will be a signed detour.
Work Hours:
- Weekdays 7:00 a.m. – 4:00 p.m.
- Weeknights 8:00 p.m. – 6:00 a.m.
- Saturday 7:00 a.m. – 7:00 p.m.
- Sunday 8:00 a.m. – 5:00 p.m.
14TH/YESLER SEGMENT – CONSTRUCTION DETAIL
Expect Traffic Delays This Week on Yesler at 10th
Weekday Work:
- Yesler – Broadway to Boren
- o Water main installation
- Yesler – 12thto 14th
- o Traffic signal work
- Jackson – 8th to 10th
- o Water main installation
Work Hours:
- Weekdays – 7:00 a.m. – 7:00 p.m.
JACKSON SEGMENT – CONSTRUCTION DETAIL
Water Main, Storm Drain, and Electrical Duct Bank Installation
Weekday Work:
- Electrical duct bank installation between 1st and 2nd
- Water main installation between 6th and 7th
- Water main installation between 8th and 10th
Weekend Work:
- Electrical duct bank and vault installation between 1st and 2nd
- Water main installation between 6th and Maynard
- Storm drain installation at 8th Avenue intersection
- Work Hours:
- Weekdays 7:00 a.m. – 4:00 p.m.
- Weekend 7:00 a.m. – 6:00 p.m.
Note on Water Main Shutoffs:
October 6th – 7th will begin the first of three weekend water shutoffs in October for the Chinatown/International District. The shutoffs will begin at 10:00 p.m. on Saturdays and continue until 10:00 a.m. on Sundays. If your building will be affected you will receive a notice directly from Seattle Public Utilities at least 72 hours in advance.
More information at http://www.seattlestreetcar.org/firsthill.htm