Seattle City Light Work near CenturyLink Field Delayed

Construction Update

 Seattle City Light Work near CenturyLink Field Delayed

Seattle City Light plans to replace some of the existing major power lines (feeders) from1st Avenue South with new ones in Occidental Avenue between Railroad Way South and South King Street. The work would prepare the area for the SR 99 Tunnel Project and the eventual removal of the Alaskan Way Viaduct along the downtown waterfront. This is an update to our previous fliers on the work.

The project is delayed and is in the planning stages.  We intend to provide customers with 3-4 weeks advance notification before the proposed start date.

Once started, the project includes two phases: civil and electrical.  The work involves trenching and building duct banks and vaults. Pulling and splicing electrical cable will follow. See accompanying map.

There are no planned power outages associated with this project. Seattle City Light will work closely with state and local agencies as well as major sporting events to coordinate detours, and uniformed police officers will direct traffic and promote access there at all times during construction.

Thank you for your patience during this feeder relocation.  For any questions you may have or for more information, contact Mark VanOss, Sr. Public Relations Specialist, at (206) 684-3279 or mark.vanoss@seattle.gov.                                                                                                                                      8/02/2012

First Hill Streetcar – Weekly Project Updates: August 13th – August 19th

First Hill Streetcar – Weekly Project Updates

This Week: August 13th – August 19th       

This post contains project updates for all three segments:  Broadway, 14th & Yesler, and the Jackson segment.

Full copies of these updates are linked above.

 

BROADWAY SEGMENT – CONSTRUCTION DETAIL

Road Reconstruction, Water Main and Storm Drain Installation

Weekday Work:

  • Howell to Pine
    • o Reconstruction of roadway between tracks
  • Union intersection
    • o Traffic signal work

• Marion intersection

  • o Storm drain and sewer main installation
  • Minor intersection
    • o Electrical duct bank installation

Weekend Work

• Jefferson intersection

  • Water main installation

Work Hours:

  • Monday – Friday 7:00 a.m. – 4:00 p.m.
  • Weekend – Continuous work from 7:00 a.m. Saturday until 5:00 p.m. Sunday

Upcoming Work:

The week of August 20th excavation and construction will begin for the trackway between Pine and Pike. Expect lane closures, no left turn at Pine for northbound traffic, and a loss of parking and loading zones.

Note Regarding Water Main Installation:

In late August there will be nighttime interruptions to water service from Cherry to Jefferson. If your building will be affected you will receive notice of a water shutdown directly from Seattle Public Utilities at least 72 hours in advance.

 

14TH/YESLER SEGMENT – CONSTRUCTION DETAIL

Expect Weekend Closure of 14th and Yesler Intersection for Concrete Paving

Weekday Work:

  • Yesler – Broadway to 10th
    • o Storm drain and sewer installation
  • Yesler – 12thto 14th
    • o Trackway construction
  • 14th– Yesler to Rainier
    • o Trackway construction
    • o Storm drain installation
    • o Electrical Installations
  • Main – 14thto Boren
    • o Electrical duct bank installation

Weekend Work:

  • Yesler and 14thintersection
    • o Intersection reconstruction

Work Hours:

  • Weekdays – 7:00 a.m. – 5:00 p.m.
  • Friday Night – 6:00 p.m. – 10:00 p.m. Expect loud impact work under a noise variance, including concrete breaking, beginning at

6:00 p.m.

  • Sunday – 8:00 a.m. – 5:00 p.m.
  • Saturday – 7:00 a.m. – 7:00 p.m.

Traffic Advisory:

The intersection of 14th and Yesler will be closed to all traffic from 6:00 p.m. on Friday, August 17th until 5:00 a.m. Monday, August 20th.

 

JACKSON SEGMENT – CONSTRUCTION DETAIL

Water Main, Storm Drain, and Electrical Duct Bank Installation

Weekday Work:

  • Electrical duct bank installation between 1st and 3rd  
  • Installation of water main between Maynard and 7th
  • Storm drain installation between 7th and 8th

Weekend Work:

  • Storm drain installation at 7th

Work Hours:

  • Monday – Friday 7:00 a.m. – 4:00 p.m.
  • Weekend 7:00 a.m. – 6:00 p.m.

Note Regarding Water Main Installation:

Beginning in late September there will be water service interruptions as new connections are made along Jackson.  If your building will be affected you will receive notice of a water shutdown directly from Seattle Public Utilities at least 72 hours in advance.

 

More information at http://www.seattlestreetcar.org/firsthill.htm

Alaskan Way Viaduct Replacement Construction Closures – Highlights for Friday, Aug. 10 – Monday, Aug. 20

Alaskan Way Viaduct Replacement Construction Closures

Visit WSDOT’s website for a complete list of closures. Closure information changes frequently, so remember to check for updates throughout the week.

Corridor-wide:

  • Viaduct reinforcement work will close all lanes of southbound SR 99 between the north end of the Battery Street Tunnel and the West Seattle Bridge at the following times:
    • 9 p.m. to 5 a.m. nightly, Sunday, Aug. 12 – the morning of Friday, Aug. 17
    • 9 p.m. to 5 a.m. Sunday, Aug. 19, Wednesday, Aug. 22, and Thursday, Aug. 23.

North:

Southbound SR 99/Aurora Avenue North long-term lane closure reopens on Aug. 13

  • Beginning Monday, Aug. 13 at 5 a.m., the right lane of southbound SR 99 will reopen between Republican and Harrison streets. The lane, along with access to and from southbound SR 99 from nearby side streets, closed in late June to allow crews room to relocate underground utilities in preparation for construction of the SR 99 tunnel’s future north portal.
  • Two right lanes of southbound SR 99 between Roy Street and the John Street/Denny Way exit will close from 7 p.m. Sunday, Aug. 12 until 5 a.m. Monday. The Denny Way exit will remain open.

Monday, Aug. 13 – Thursday, Aug. 16

  • Sixth Avenue North will be closed between Harrison and Thomas streets from 7 a.m. to 5 p.m. daily.
  • John Street will be closed between Sixth Avenue North and Taylor Avenue North from 7 a.m. to 5 p.m. daily.

Friday, Aug. 17

  • Sixth Avenue North will be closed between John and Thomas streets from 7 a.m. to 5 p.m. daily. Local access will be maintained using Thomas Street.

Sunday, Aug. 19 – the morning of Monday, Aug. 20

  • ·Sixth Avenue North will be closed between Harrison and Thomas streets from 8 p.m. to 5 a.m. Local access will be maintained using Thomas Street.

Central:

  • The southbound roadway under the viaduct will be closed nightly from Marion Street to Yesler Way, from 7 p.m. to 5 a.m. Sunday, Aug. 12 through the morning of Friday, Aug. 17.

South:

  • The right lane of northbound SR 99 between South Hanford Street and South Royal Brougham Way will be closed from 8 p.m., Friday, Aug. 10 through 7 a.m., Saturday morning.

Quick links:

 

Website links

Alaskan Way Viaduct Replacement Program

SR 99 Tunnel Project | South Holgate Street to South King Street Project