Alaskan Way Viaduct Replacement Construction Closures – Highlights for Monday, June 4 – Saturday, June 9

Visit WSDOT’s website for a complete list of closures. Closure information changes frequently, so remember to check for updates throughout the week.

Highlights for Monday, June 4 – Saturday, June 9

North end:

  • John Street will close between Taylor Avenue North and Sixth Avenue North from 7 a.m. to 7 p.m. Monday through Saturday for utility work. Alley access will be maintained.
  • Sixth Avenue North will close between Harrison Street and Thomas Street around-the-clock from at 7 a.m. Monday to 5 p.m. Friday for utility work.

Central waterfront:

  • The lanes adjacent to bus-stop islands on Alaskan Way and in the ferry holding area will close between Madison and Columbia streets from 7 a.m. to 5 p.m. Monday through Friday.
  • Flaggers will alternate traffic in the intersection of Yesler Way and the road under the viaduct from 9 p.m. to 5 a.m. Monday through Friday.

South end:

  • East Marginal Way South will close between South Atlantic Street to South Massachusetts Street from 7 p.m. Monday to 5 a.m. Tuesday. Local access will be maintained.

Quick links:

Website links

Alaskan Way Viaduct Replacement Program

SR 99 Tunnel Project | South Holgate Street to South King Street Project